Elkem Furnace 15 Upgrade
Client:Elkem MetalsLocation:Alloy, WVValue of Project:$13 MValue of Work:$350 KDescription:
Harold Totten, Augusta’s Lead Power Engineer and a team of Augusta’s electrical and civil/ structural draftsmen were in charge of selecting the vendor, specifying all the equipment and performing the detailed installation design work. The Augusta team also oversaw the installation, as well as assisted in the start-up. During the project the Furnace 15 unit was temporarily shut down which determined the very aggressive schedule; as the unit needed to be back on-line within six months to meet silicone production needs. |
|